PLANNING REQUIREMENTS FOR CONTAMINATED LAND

EPPING FOREST DISTRICT COUNCIL

At Sequoia Environmental, we undertake a lot of work within the Epping Forest district.  Proposals for new residential development in this area often attract planning conditions for contamination, particularly on former agricultural, industrial and ex-military land.  This section provides a developer's guide to fulfilling the council's planning requirements for contamination.

WHAT DOES THE CONDITION LOOK LIKE?

Planning conditions for contamination applied by Epping Forest District Council (EFDC) usually comprise up to five parts, with requirement for the following work:

  1. Phase I Land Contamination Investigation

  2. Phase II Site Investigation

  3. Remediation Works

  4. Verification Report

  5. Reporting of Unexpected Contamination

 

If on completion of any of these phases, it can be demonstrated that the level of risk to future site users or the surrounding environment is acceptable, then the remaining work would not be required, and the condition can be discharged.

For example, if the Phase I Land Contamination Investigation identified that a site had comprised a potentially contaminative historic use, then a Phase II Site Investigation would be necessary.  However, if this subsequent investigation did not identify the presence of any contamination, then no further remediation or verification would be required.

EFDC’s standard land contamination conditions can be viewed in full on their website.

WHY HAS THE CONDITION BEEN ADDED?

Planning Permission

In accordance with the National Planning Policy Framework (NPPF) the responsibility for safe development lies with the developer or landowner.  If a site has been affected by contamination or comprises a sensitive end use, then some environmental assessment is likely to be necessary.  Conditions for contamination are usually applied either where the potential for contamination exists (i.e. former commercial or industrial land use) or where a sensitive end use (i.e. residential) is proposed.

MY SITE IS NOT COMMERCIAL/INDUSTRIAL - WHY DO I NEED TO PROVIDE A CONTAMINATION ASSESSMENT?

Woman thinking

In this instance, it’s likely that the condition has been added due to the site’s historic use – EFDC hold historic maps and land use records dating back to the nineteenth century and former uses may not be obvious.

Alternatively, a contamination assessment may be required where a sensitive end-use is proposed.  Residential development is classified as a sensitive end use and so a basic assessment may be required for proposed residential sites even where no historic uses have been identified.

WHAT DO I NEED TO DO TO COMPLY WITH THE CONDITION?

Checklist

Unless one has been completed at the pre-application stage, the first piece of work necessary is a Phase I Land Contamination Investigation, also known as a Desk Study.  Check out the Desk Study section of our website for more information on the process.  On completion of each phase of work, the relevant details should be submitted to EFDC with an application to discharge the relevant condition.  Each phase of work should be approved in writing be EFDC prior to commencement of the next.

CAN I SUBMIT AN ENVIRONMENTAL PROPERTY SEARCH?

Outline of Chimneys

Property searches, such as Landmark Envirosearch etc. can be very useful during the conveyancing process. However, they do not fulfil the requirements for environmental assessment as set out within DEFRA and Environment Agency guidance CLR11.  Crucially, these reports don’t include a risk assessment and development of a Conceptual Site Model.  You can find out more about the Conceptual Site Model on our website.

WHAT SHOULD BE INCLUDED WITH THE DESK STUDY?

EFDC have produced a protocol for the items to be included within a Phase I report. This information is available on their website and is summarised below:

  1. Basic site information including site location, ownership, size and description.

  2. Basic screening data including historic maps, aerial photographs, geological records and information obtained from the EFDC planning and environmental databases.

  3. Site reconnaissance including collection of site photographs and completion of an on-site checklist.

  4. Outline conceptual site model including development of a contaminant linkage assessment and preliminary risk assessment.

WHAT AREA SHOULD BE COVERED?

Building Plan

Environmental assessment should be undertaken for all parts of the site that lie within the planning boundary (i.e. the ‘red line’).  The reason for this is that once a site has passed through the planning system, it can't then be classified as 'Contaminated Land' under Part IIA of the Envrionmental Protection Act (1990).

HOW LONG DOES A DISCHARGE OF CONDITION TAKE?

Calendar

Upon completion, reports should be submitted to the planning officer as part of a discharge of the relevant condition.  The Contaminated Land Officer will then be consulted by the planners.  Once the application to discharge the condition is validated, the determination period will be confirmed (this can vary but is usually 8 weeks for smaller applications).